      San Gabriel: What’s Going On at Del Mar Avenue and Valley Boulevard?

      construction equipment and workers on a street

      Intersection of Del Mar Ave. and Valley Blvd. in San Gabriel (Photo – sangabrielcity.com)

      The Valley Blvd and Del Mar Avenue intersection is currently undergoing major construction work – including overhead utility lines being relocated underground, sewer pipes being replaced, and Del Mar Avenue being paved.

      By News Desk

      Lane reductions and traffic delays are expected for the next year or so. The City of San Gabriel is encouraging residents to seek alternative routes or leave earlier if they are traveling through the intersection.

      Phase 1 – Utility Line Relocated Underground (Completed)

      All overhead utility lines adjacent to the project site and crossing Valley Blvd have been moved underground. This was completed in late 2022 and is part of the hotel development project on the northwestern corner of Valley Blvd and Del Mar Avenue.

      Phase 2 – Sewer Rehabilitation (Current Phase)

      As the existing sewer pipe is flowing very near capacity, the City is installing a new, larger sewer line across Valley Blvd. This phase is expected to be completed around February 2023.

      Phase 3 – Paving of Del Mar Avenue (2023-2024)

      Once the sewer work is completed, the City will contract paving work to resurface Del Mar Ave on both sides of Valley Blvd. The intersection itself will be repaved in the next phase.

      Phase 4 – Paving of Intersection and Improvements on Valley Blvd (2024 and Onwards)

      The intersection of Del Mar Avenue and Valley Blvd will be fully reconstructed in 2024 as San Gabriel’s Measure R-funded intersection projects with Metro begin. Other improvements include new traffic signals, controller cabinets, widening lanes and crosswalks. The intersections of Valley Blvd at New Ave and at San Gabriel Blvd will also be included in this project, which will improve traffic flow along Valley Blvd.

      There is still a lot of work to be done, but a very nice ending for this busy intersection is in sight.

       

      Source: City of San Gabriel. Edited by Ann Hunnewell

      Support Independent Local Journalism This Holiday Season

      We hope you enjoyed this article. We live in and care deeply about this community, and we’re grateful to be part of it.

      For more than a decade, Colorado Boulevard Newspaper has investigated local issues, asked difficult questions, and worked to hold power accountable; free from shareholders, corporate agendas, and outside influence..

      Your support helps make the time, research, and reporting behind these stories possible.

      A $5 gift or subscription can help keep independent local journalism strong, this holiday season and all year long.

      Please explore the many ways to support us by clicking the button below.

      Support

      Author

      Leave a Reply

      Your email address will not be published. Required fields are marked *