The San Gabriel City Council is weighing major changes to its aging police facilities, with plans ranging from renovation to full reconstruction, as officials say the current space no longer meets the department’s needs.
By Zamourad Iqbal
At a meeting Tuesday, March 17, the council reviewed five conceptual development scenarios and unanimously approved mid-year budget adjustments for fiscal year 2025–2026.
Dustin Alamo, a certified construction manager with Griffin Structures, presented the proposed police facility project, outlining five scenarios with varying levels of renovation, expansion, and new construction. The plans focus on meeting the department’s operational needs, parking requirements, and compliance with current seismic standards.
The presentation also detailed the limitations of the existing facility.
“The department’s current space is 16,500 square feet, which is insufficient for future needs,” Alamo said. “Their analysis shows they will require about 32,500 square feet for basic growth, with up to 40,000 square feet to meet best practices, including support facilities such as training and evidence storage.”
During the workshop, councilmembers raised concerns about funding mechanisms, facility longevity, future growth, and overall costs.
According to the discussion, public safety bond measures are the most common funding method, though other financing options may also be considered.
Vice Mayor Eric L. Chan asked whether a jail facility was included in the proposal, citing ongoing concerns and questions.
According to the Griffin Structures plan, jail facilities are not included due to liability concerns, including the challenges of managing multiple prisoners and providing medical care.
Budget Update
City Finance Director Will Kaholokula also presented a midyear budget update for fiscal year 2025–26.
According to the General Fund report, revenues are projected to increase by $24,000 to $57.7 million, while expenditures are expected to rise to $59.2 million.
“General Fund revenues are projected to be $24,000 higher than the adopted budget,” Kaholokula said. “The major categories with changes at this midyear point are taxes, our largest revenue source, which are projected to be $494,000 lower than the adopted budget.”
Kaholokula added that the Mission Playhouse is facing a projected $37,000 deficit, which will be offset by a $185,000 transfer from the General Fund. He also noted that the retirement fund is facing a $938,938 deficit due to CalPERS pension costs outpacing revenue.
Councilmembers emphasized the importance of maintaining strong reserve levels and highlighted the city’s overall financial stability.
The council then approved Resolution 2606, authorizing a $185,000 transfer from the General Fund to the Mission Playhouse and other midyear adjustments totaling $318,000. The motion passed 5–0.
The next City Council meeting is scheduled for April 7.